Project Description:
WESTFORD- INTERSECTION & SIGNAL IMPROVEMENTS AT ROUTE 110 (LITTLETON ROAD) & ROUTE 225 (CONCORD ROAD)
The Town of Westford is proposing to widen approximately 3,000 feet of Littleton Road (Route 110). The existing cross section contains one lane in each direction with an additional left turn lane for approximately 400 feet. The proposed roadway will be widened to provide a cross section with two lanes in each direction with an additional left turn lane for approximately 900 feet. Three (3) new traffic signals will be installed at the intersection of Route 110 with: (1) Concord Road (Route 225 W) (2) #310 Littleton Road Site Driveway (3) Concord Road (Route 225 E). The project will also include landscaping improvements and pedestrian connections with a new sidewalk being constructed for the entire length of the corridor.
Location:
  • Town of Westford
  • Resident Engineer: Patrick Marion
    Construction Contract Value: $2,708,749.00
    Construction Bid Price: $2,458,181.35
    Initial Construction Estimate: $3,431,985.00
    District: District 3

    Contracts (1) Progress
    # 59252 -- Construction Contract
    Intersection Imptovements and Related Work Route 110 (Littleton Road) at Route 225 (Concord Road) EB & WB. (ARRA Project) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/06/2009
    Contract Information
    Project Designer: Other
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/02/2009
    Project Initiation Form PIF Entered 03/02/2009
    Project Initiation Form PRC Submitted 03/02/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Status Advertised 06/20/2009
    Project Management
    100% Design 100% Package Received 03/19/2009
    100% Design 100% Package Comments to DE 04/28/2009
    Final Design PS&E Received 06/16/2009
    Final Design PS&E to FAPRO 06/16/2009