Project Description:
AMHERST- RESURFACING & RELATED WORK ON ROUTE 116
Work under this project will consist of micromilling 1.5” from the existing paved surface and repaving with a 1.5” asphalt standard top course and a 0.75" paver placed friction course. Work will also include partial and full depth pavement repairs as needed along with new pavement markings. The project limits are as follows: Route 116 from mm 16.30 to 17.03 and from mm 17.28 to 19.04 for a project length of 2.49 miles.
Location:
  • Town of Amherst
  • Resident Engineer: Michael DeSimone
    Construction Contract Value: $1,721,274.00
    Construction Bid Price: $1,477,784.60
    Initial Construction Estimate: $1,822,423.20
    District: District 2

    Contracts (1) Progress
    # 62154 -- Construction Contract
    Resurfacing and Related Work on Sections of Route116. (ARRA Project) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/11/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/23/2009
    Project Initiation Form PIF Entered 04/02/2009
    Project Initiation Form PRC Submitted 04/07/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 06/05/2009
    Project Status Advertised 12/26/2009
    Project Management
    25% Design 25% Package Received 10/27/2009
    25% Design 25% Package Comments to DE 11/04/2009
    25% Design 25% Plans Complete 11/23/2009
    75% Design 75% Package Received 11/24/2009
    75% Design 75% Package Comments to DE 12/03/2009
    Final Design PS&E Received 12/17/2009
    Final Design PS&E to FAPRO 12/21/2009