WORCESTER- SIDEWALK CONSTRUCTION ON MCKEON ROAD
The McKeon Road sidewalk construction project begins at Holy Cross Stadium and extends 4,242 linear feet (0.80 miles) to Butler Street. The project involves sidewalk construction, lighting installation and minor roadway work.
Location:
  • City of Worcester
  • Resident Engineer: Robert Cullinan Jr.
    Construction Contract Value: $1,054,054.00
    Construction Bid Price: $1,046,438.60
    Initial Construction Estimate: $951,026.25
    District: District 3

    Contracts (2) Progress
    # 64323 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 80856 -- Construction Contract
    Sidewalk Construction, Street Lighting and Related Work on a Section of McKeon Road. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/09/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: SECTION 129
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/23/2009
    Project Initiation Form PIF Entered 03/23/2009
    Project Initiation Form PRC Submitted 04/09/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Status Advertised 12/28/2013
    Project Management
    100% Design 100% Package Received 05/06/2013
    100% Design 100% Package Comments to DE 07/11/2013
    25% Design 25% Package Received 06/10/2011
    25% Design 25% Package Received 08/08/2012
    25% Design 25% Package Comments to DE 09/17/2012
    25% Design 25% Package Rejected 09/30/2011
    25% Design Design Public Hearing 12/19/2012
    Final Design PS&E Received 11/04/2013
    Final Design PS&E to FAPRO 12/23/2013