Project Description:
LEOMINSTER- RECONSTRUCTION ON ROUTE 13, FROM HAWES STREET TO PROSPECT STREET
The project involves reconstruction and widening of a section of Route 13 from Hawes Street to Prospect Street, a distance of 0.6 miles. The project involves a new signal at Route 13 and Mead, as well as signal equipment upgrades and coordination of existing signals. The proposed improvements will address safety at the Route 13 and Prospect Street intersection, which is identified as #35 on the list of high crash locations across the Commonwealth.
Location:
  • City of Leominster
  • Construction Begins: Autumn 2020
    Resident Engineer: Patrick Marion
    Construction Bid Price: $4,831,129.50
    District: District 3

    Contracts (5) Progress
    # 112085 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 13 (Main Street) Completed
    # 51303 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57733 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64321 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77884 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/05/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/23/2009
    Project Initiation Form PIF Entered 08/05/2009
    Project Initiation Form PRC Submitted 08/10/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/03/2009
    Project Status Advertised 07/18/2020
    Project Management
    100% Design 100% Package Received 07/23/2018
    100% Design 100% Package Comments to DE 11/02/2018
    25% Design 25% Package Received 02/02/2012
    25% Design 25% Package Comments to DE 12/10/2012
    25% Design Design Public Hearing 12/03/2013
    75% Design 75% Package Received 08/07/2017
    75% Design 75% Package Comments to DE 10/06/2017
    Final Design PS&E Received 05/20/2019
    Final Design PS&E Received - Resub 1 10/08/2019
    Final Design PS&E Received - Resub 2 01/29/2020