CAMBRIDGE- NEWTON- FIBER OPTIC CONNECTION AT THREE LOCATIONS (ITS)
The purpose of this project is to provide fiber optic connectivity at three locations. Location 1: District 4 Headquarters via Rte 2 to MBTA Alewife station in Cambridge. Location 2: Rte 128 Rest Area in Newton to MBTA's Riverside Station. Location 3: MEMA bunker to MTA toll plaza in Framingham.
Location:
  • City of Cambridge
  • City of Newton
  • Resident Engineer: Daniel Rychalsky
    Construction Contract Value: $2,058,407.00
    Construction Bid Price: $1,736,734.00
    Initial Construction Estimate: $1,512,528.18
    District: District 4

    Contracts (3) Progress
    # 51301 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57731 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 61342 -- Construction Contract
    Fiber Optic Network (ITS) Installation Along I-95/Route 128, Route 2 and Other Locations. (ARRA Projects) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/17/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/24/2009
    Project Initiation Form PIF Entered 03/24/2009
    Project Initiation Form PRC Submitted 03/24/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 05/19/2009
    Project Status Advertised 09/19/2009
    Project Management
    100% Design 100% Package Received 06/09/2009
    Final Design PS&E Received 06/22/2009
    Final Design PS&E to FAPRO 06/24/2009