Project Description:
MEDWAY- RECONSTRUCTION ON ROUTE 109, FROM HOLLISTON STREET TO 100 FT. WEST OF HIGHLAND STREET, INCLUDES REHAB OF M-13-012
The Route 109 reconstruction project in Medway will focus on roadway improvements in Medway’s business district including resurfacing and reconstruction, consolidating curb cuts, sidewalks, signage, street lighting, and aesthetic improvements. Signal upgrade and capacity improvements will be implemented at the intersection of Main, Franklin, Milford, and Highland Streets, including widening for turn lanes in the SB and WB approaches. Work also includes adjusting the grade on Main Street west of Winthrop Street for approximately 700 feet.
Location:
  • Town of Medway
  • Resident Engineer: Julio Fontecchio
    Construction Bid Price: $9,581,391.20
    District: District 3

    Contracts (1) Progress
    # 90474 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals and Rehabilitation of Br. No. M-13-012) along a Section of Route 109 (Main Street) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/06/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/24/2009
    Project Initiation Form PIF Entered 04/07/2009
    Project Initiation Form PRC Submitted 04/09/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 06/08/2009
    Project Status Advertised 09/05/2015
    Project Management
    100% Design 100% Package Received 03/24/2015
    100% Design 100% Package Comments to DE 05/13/2015
    25% Design 25% Package Received 09/22/2011
    25% Design Design Public Hearing 05/01/2013
    75% Design 75% Package Received 03/03/2014
    75% Design 75% Package Comments to DE 05/19/2014
    Final Design PS&E Received 07/31/2015
    Final Design PS&E Received 10/15/2015
    Final Design PS&E Received 01/27/2016
    Final Design PS&E to FAPRO 09/02/2015
    Final Design PS&E to FAPRO 02/01/2016