MANSFIELD- CORRIDOR IMPROVEMENTS ON ROUTE 106 (EASTMAN STREET), FROM EAST STREET TO THE EASTON T.L.
Work on this project consists of minor widening, milling and resurfacing, sidewalk construction and reconstruction, safety improvements at intersections, and drainage upgrades. The length of the project is 0.9 miles. Intersection improvements shall include turning lanes and acceleration lanes, blinking traffic signals, street lighting and signage.
Location:
  • Town of Mansfield
  • Resident Engineer: John Bielski
    Construction Contract Value: $1,834,905.00
    Construction Bid Price: $1,576,119.59
    Initial Construction Estimate: $2,063,786.00
    District: District 5

    Contracts (1) Progress
    # 73148 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Route 106 (Eastman Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/13/2012
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/01/2009
    Project Initiation Form PIF Entered 04/01/2009
    Project Initiation Form PRC Submitted 04/21/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 06/09/2009
    Project Status Advertised 03/24/2012
    Project Management
    100% Design 100% Package Received 02/01/2012
    25% Design 25% Package Received 01/29/2010
    25% Design 25% Package Comments to DE 03/15/2010
    25% Design Design Public Hearing 01/19/2011
    75% Design 75% Package Received 07/25/2011
    75% Design 75% Package Comments to DE 11/15/2011
    Final Design PS&E Received 03/19/2012
    Final Design PS&E to FAPRO 03/19/2012