Project Description: |
DISTRICT 5- SALT STORAGE SHED REPAIRS AT VARIOUS LOCATIONS
This contract is used to repair and maintain District-wide salt sheds. Maintaining our facilities helps meet our environmental compliance BMP's. Properly maintained facilities protects our materials from the weather.
|
Location: | |
Resident Engineer: | Kenneth Charlton |
Construction Contract Value: | $789,662.95 |
Construction Bid Price: | $526,700.00 |
Initial Construction Estimate: | $471,800.00 |
District: | District 5 |
|