Project Description:
RAYNHAM- SIGNAL & INTERSECTION IMPROVEMENT @ ROUTE 44 (NEW STATE HIGHWAY), ORCHARD STREET & ROUTE 24 (NB) OFF-RAMP
Work on this intersection improvement project in Raynham consists of traffic signal installation and reconstruction at the Route 44/Orchard Street intersections.
Location:
  • Town of Raynham
  • Resident Engineer: Matthew Lambert
    Construction Contract Value: $3,304,631.00
    Construction Bid Price: $2,747,251.00
    Initial Construction Estimate: $2,524,342.00
    District: District 5

    Contracts (3) Progress
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 81431 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 44 (New State Highway), Orchard Street and Route 24 NB Off Ramp. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/04/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/02/2009
    Project Initiation Form PIF Entered 04/02/2009
    Project Initiation Form PRC Submitted 04/21/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 06/09/2009
    Project Status Advertised 03/15/2014
    Project Management
    100% Design 100% Package Received 08/02/2013
    100% Design 100% Package Comments to DE 10/04/2013
    25% Design 25% Package Received 12/02/2011
    25% Design 25% Package Comments to DE 06/01/2012
    25% Design 25% Package Approved 08/24/2012
    25% Design Design Public Hearing 09/17/2012
    75% Design 75% Package Received 11/30/2012
    75% Design 75% Package Comments to DE 02/22/2013
    Final Design PS&E Received 11/04/2013
    Final Design PS&E Received 12/06/2013
    Final Design PS&E to FAPRO 12/17/2013