Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WALES - PEDESTRIAN ACCESS IMPROVEMENTS & RELATED WORK ON ROUTE 19
The project includes reconstruction of sidewalks and other pedestrian access improvements along a 1.5 mile section of Route 19 in the Town of Wales, from mile marker 2.51 to mile marker 4.03. The work is predominantly in the town center area and includes reconstruction of sidewalks, wheelchair ramps, curbing and drainage alterations, pavement and markings, and other associated work. All work will comply with the Architectural Access Board (AAB), the Americans with Disabilities Act (ADA) and current MassDOT standards.
Location:
  • Town of Wales
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Greg Frazier
    Estimated Total Contract Cost: $275,000.00
    Estimated Total Federal Participating Construction Cost: $312,500.00
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/02/2009
    Project Initiation Form PIF Entered 04/07/2009
    Project Initiation Form PRC Submitted 04/10/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 06/08/2009
    Project Management