Project Description:
FALMOUTH- INTERSECTION IMPROVEMENTS AT EAST FALMOUTH HIGHWAY (ROUTE 28), DAVISVILLE ROAD & OLD MEETINGHOUSE ROAD AND INTERSECTION IMPROVEMENTS AT TEATICKET HIGHWAY (ROUTE 28) AND JONES ROAD/WORCESTER COURT
This project is intended to improve safety through the implementation of intersection improvements, traffic signal upgrades, and minor geometric improvements. Related work includes sidewalk installation, minor drainage improvements, pavement markings and new signage.
Location:
  • Town of Falmouth
  • Resident Engineer: Richard McKenzie
    Construction Contract Value: $3,269,348.00
    Construction Bid Price: $2,787,720.00
    Initial Construction Estimate: $2,566,871.77
    District: District 5

    Contracts (3) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 79738 -- Construction Contract
    Intersection Improvements and Related Work at 2 Locations along Route 28 (Davisville and Old Meetinghouse Roads; Jones Road and Worcester Court) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/25/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/06/2009
    Project Initiation Form PIF Entered 10/08/2009
    Project Initiation Form PRC Submitted 10/20/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Status Advertised 09/14/2013
    Project Management
    100% Design 100% Package Received 04/11/2013
    100% Design 100% Package Comments to DE 06/14/2013
    25% Design 25% Package Received 07/05/2011
    25% Design 25% Package Comments to DE 12/19/2011
    25% Design Design Public Hearing 05/17/2012
    75% Design 75% Package Received 10/24/2012
    75% Design 75% Package Comments to DE 12/21/2012
    Final Design PS&E Received 08/12/2013
    Final Design PS&E to FAPRO 09/10/2013