Project Description:
ARLINGTON- CAMBRIDGE- SOMERVILLE- ALEWIFE GREENWAY CORRIDOR RESTORATION (AKA MINUTEMAN BIKE PATH CONNECTOR)
An 8'-10'-wide stabilized aggregate path, asphalt and elevated boardwalk are planned on both the eastern and western sides of Alewife Brook between Route 2 and Mystic Valley Parkway. In order to avoid an existing cemetery, no pathway is proposed between Henderson Avenue and Broadway Avenue. Boardwalk installation is planned to occur in areas recognized as being particularly sensitive to foot-traffic (e.g., adjacent to and through isolated vegetated wetland). Invasive plants will be selectively removed in targeted locations within the project area.
Location:
  • Town of Arlington
  • City of Cambridge
  • City of Somerville
  • Design Responsibility: Other
    Right of Way Responsibility: Other
    Project Manager: Albert Miller
    Estimated Total Contract Cost: $4,360,304.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 6
    Current Status: This project has been advertised for construction bids. (as of 01/30/2010 )

    Contracts (1) Progress
    # 54620 -- Design -- Geotechnical
    Work will consist of laboratory and field testing, subsurface investigation inspection, and design and analysis of complex foundation rehabilitation projects. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/06/2009
    Project Initiation Form PIF Entered 04/07/2009
    Project Initiation Form PRC Submitted 04/13/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 05/19/2009
    Project Status Advertised 01/30/2010
    Project Management
    100% Design 100% Package Received 08/24/2009
    100% Design 100% Package Comments to DE 11/16/2009
    75% Design 75% Package Received 05/04/2009
    75% Design 75% Package Comments to DE 07/06/2009
    Final Design PS&E Received 01/22/2010
    Final Design PS&E to FAPRO 01/22/2010