Project Description:
MATTAPOISETT- MULTI-USE PATH CONSTRUCTION (PENN CENTRAL RIGHT OF WAY), FROM MATTAPOISETT NECK ROAD TO DEPOT STREET (PHASE 1B)
Work will consist of construction of a multi-purpose path. The path will connect to the existing multi-purpose path at Mattapoisett Neck Road and will terminate at Depot Street. This is the second phase of multiple phased path proposed through the Town of Mattapoisett.
Location:
  • Town of Mattapoisett
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Alfredo Nunez
    Construction Bid Price: $6,645,395.44
    District: District 5

    Contracts (2) Progress
    # 105770 -- Construction Contract
    Construction of Phase 1B of a Shared Use Path from Mattapoisett Neck Road to Depot Street Including Bridge Nos. M-09-010 and M-09-011 Completed
    # 77845 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 02/20/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/09/2009
    Project Initiation Form PIF Entered 04/09/2009
    Project Initiation Form PRC Submitted 05/01/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 06/22/2009
    Project Status Advertised 09/01/2018
    Project Management
    100% Design 100% Package Received 02/16/2017
    100% Design 100% Package Comments to DE 04/18/2017
    100% Design 100% Package Received - Resub 1 08/01/2017
    25% Design 25% Package Received 02/19/2010
    25% Design 25% Package Received 04/12/2012
    25% Design 25% Package Received 06/23/2014
    25% Design 25% Package Received 11/01/2016
    25% Design 25% Package Comments to DE 01/27/2016
    25% Design 25% Package Comments to DE 01/27/2016
    25% Design Design Public Hearing 09/25/2014
    Final Design PS&E Received 05/31/2018
    Final Design PS&E to Peer Reviewer 03/19/2018
    Final Design Peer Review Comments to DE 03/26/2018
    Final Design PS&E Received - Resub 1 07/17/2018
    Final Design PS&E Received - Resub 2 08/01/2018
    Final Design PS&E Received - Resub 3 08/10/2018
    Final Design PS&E Received - Resub 4 08/15/2018