NEW BEDFORD- CONSTRUCTION OF FLAHERTY DRIVE EXTENSION, INCLUDES WILDLIFE CULVERTS N-06-044 & N-06-045
Work on this project consists of the construction of approximately 900 linear feet of roadway, extending from Flaherty Drive with associated utilities to service a proposed industrial parcel containing approximately 46 acres of land in the City of New Bedford.
Location:
  • City of New Bedford
  • Resident Engineer: David Ribeiro
    Construction Contract Value: $946,608.00
    Construction Bid Price: $1,647,524.71
    Initial Construction Estimate: $1,885,124.40
    District: District 5

    Contracts (2) Progress
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 73156 -- Construction Contract
    Construction of the Flaherty Drive Extension (Including 2 Wildlife Culverts). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/19/2012
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/09/2009
    Project Initiation Form PIF Entered 04/09/2009
    Project Initiation Form PRC Submitted 04/21/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Status Advertised 03/31/2012
    Project Management
    100% Design 100% Package Received 12/20/2011
    100% Design 100% Package Comments to DE 01/26/2012
    25% Design 25% Package Received 10/19/2010
    25% Design 25% Package Comments to DE 02/15/2011
    25% Design Design Public Hearing 04/12/2011
    75% Design 75% Package Received 07/08/2011
    75% Design 75% Package Comments to DE 09/09/2011
    Final Design PS&E Received 02/17/2012
    Final Design PS&E to FAPRO 03/28/2012