Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
TAUNTON- INTERSECTION IMPROVEMENTS AT COUNTY STREET (ROUTE 140) AND HART STREET
Work on this project consists of traffic signal and geometric improvements at the intersection of County Street (Route 140) and Hart Street. This location experiences a high rate of thru versus left-turn crashes along County Street. The lane configuration and traffic signal system will be upgraded to accommodate the high volume of left-turns. The project also provides improvements for bicycle and pedestrian accommodations in compliance with MassDOT’s Complete Street Policy and the Americans for Disabilities Act. Drainage improvements, pavement markings and sign installation and incidental work associated with the project are included as well.
Location:
  • City of Taunton
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Amy Aveiro
    Construction Bid Price: $2,261,531.36
    District: District 5

    Contracts (2) Progress
    # 86005 -- Design -- Services
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 97777 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Route 140 (County Street) and Hart Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/17/2017
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/09/2009
    Project Initiation Form PIF Entered 04/13/2009
    Project Initiation Form PRC Submitted 04/21/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 06/09/2009
    Project Status Advertised 09/10/2016
    Project Management
    100% Design 100% Package Received 03/18/2016
    100% Design 100% Package Comments to DE 05/02/2016
    25% Design 25% Package Received 07/29/2011
    25% Design 25% Package Received 07/03/2014
    25% Design 25% Package Comments to DE 11/13/2013
    25% Design 25% Package Comments to DE 11/26/2014
    25% Design Design Public Hearing 05/27/2015
    75% Design 75% Package Received 08/19/2015
    75% Design 75% Package Comments to DE 11/13/2015
    Final Design PS&E Received 07/29/2016
    Final Design PS&E Received 09/06/2016
    Final Design PS&E to Peer Reviewer 07/29/2016
    Final Design Peer Review Comments to DE 08/16/2016
    Final Design PS&E to FAPRO 09/06/2016