Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CAMBRIDGE- INTERSECTION & SIGNAL IMPROVEMENTS ON BROADWAY, FROM THIRD STREET TO AMES STREET (KENDALL SQUARE)
The goal of the project is to improve safety and enhance traffic and pedestrian movement through Kendall Square at the MBTA Station area. The project involves the reconstruction and/or resurfacing of roadway and sidewalk on Broadway between Third Street and Ames Street in Cambridge. Roadway drainage, landscaping and lighting are also included in the project.
Location:
  • City of Cambridge
  • Resident Engineer: Patrick Finn
    Construction Contract Value: $722,179.00
    Construction Bid Price: $1,088,174.50
    Initial Construction Estimate: $1,066,025.00
    District: District 6

    Contracts (2) Progress
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 74407 -- Construction Contract
    Intersection Improvements and Related Work (Including Traffic Signals) on a Section of Broadway at Kendall Square. RE-ADVERTISED 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/09/2012
    Contract Information
    Project Designer: Municipality
    Funding Source: Section 117
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/14/2009
    Project Initiation Form PIF Entered 04/14/2009
    Project Initiation Form PRC Submitted 04/14/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/03/2009
    Project Status Advertised 09/17/2011
    Project Status Advertised 07/14/2012
    Project Management
    100% Design 100% Package Received 05/10/2011
    25% Design 25% Package Received 09/10/2009
    25% Design 25% Package Comments to DE 07/07/2010
    25% Design Design Public Hearing 01/26/2011
    25% Design Design Public Hearing 03/15/2011
    75% Design 75% Package Received 10/13/2010
    75% Design 75% Package Comments to DE 12/20/2010
    Final Design PS&E Received 08/12/2011
    Final Design PS&E to FAPRO 07/05/2012