Project Description:
MERRIMAC- RESURFACING & RELATED WORK ON ROUTE 110
Work on this project consists of resurfacing sections of Route 110 starting at the Haverhill-Merrimac town line and continuing easterly to end near the intersection of Orchard Street.
Location:
  • Town of Merrimac
  • Resident Engineer: Raymond Orsini
    Construction Contract Value: $525,969.00
    Construction Bid Price: $456,922.60
    Initial Construction Estimate: $472,197.50
    District: District 4

    Contracts (1) Progress
    # 75710 -- Construction Contract
    Resurfacing and Related Work (Including Sidewalks) along a Section of Route 110 (West Main Street). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/15/2013
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/16/2009
    Project Initiation Form PIF Entered 05/13/2009
    Project Initiation Form PRC Submitted 05/13/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 06/08/2009
    Project Status Advertised 09/22/2012
    Project Management
    100% Design 100% Package Received 04/16/2010
    100% Design 100% Plans Complete 04/16/2010
    75% Design 75% Package Received 06/05/2009
    75% Design 75% Package Comments to DE 06/12/2009
    Final Design PS&E Received 09/17/2010
    Final Design PS&E Received 03/30/2011
    Final Design PS&E Received 04/25/2012
    Final Design PS&E Received 05/09/2012
    Final Design PS&E Received 09/24/2012
    Final Design PS&E to FAPRO 09/11/2012