Project Description:
PITTSFIELD- RESURFACING & RELATED WORK ON BARKER ROAD & VALENTINE ROAD
The proposed project consists of pavement preservation measures to resurface approximately 8.5 miles of roadways curb to curb on First Street, Baker Road, Holmes Road and Valentine Road. The limits of pavement resurfacing on Barker Road shall extend northerly from the Richmond/Pittsfield Town Line to the northerly limit at 290 feet south of West Housatonic Street for project length of 16,200 feet. The limits of pavement resurfacing on Valentine Road shall extend northerly from 200 feet north of West Street to the northerly limit at Peck’s Road for project length of 9,600 feet. The total project length will be 27,800 feet or 5.3 miles. No additional work beyond curb line is proposed.
Location:
  • City of Pittsfield
  • Resident Engineer: Christopher Dindio
    Construction Contract Value: $2,584,478.00
    Construction Bid Price: $2,339,117.00
    Initial Construction Estimate: $2,265,139.50
    District: District 1

    Contracts (1) Progress
    # 62670 -- Construction Contract
    Resurfacing and Related Work on Barker and Valentine Roads. (ARRA Project) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/18/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/22/2009
    Project Initiation Form PIF Entered 04/29/2009
    Project Initiation Form PRC Submitted 04/29/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 06/05/2009
    Project Status Advertised 01/30/2010
    Project Management
    100% Design 100% Package Received 12/21/2009
    25% Design 25% Package Received 10/29/2009
    25% Design 25% Package Comments to DE 11/23/2009
    Final Design PS&E Received 12/30/2009
    Final Design PS&E to FAPRO 01/14/2010