Project Description:
LOWELL- METHUEN- TRAFFIC SIGN REPLACEMENT & RELATED WORK ON I-495
This project will replace and update all existing directional and traffic signs on Interstate Route 495 between State Route 38 (Exit 38) in Lowell and State Route 213 (Exit 47) in Methuen, including applicable signing on intersection roadways.
Location:
  • City of Lowell
  • Town of Methuen
  • Resident Engineer: Robert Blackmar
    Construction Contract Value: $3,178,358.00
    Construction Bid Price: $2,742,507.69
    Initial Construction Estimate: $3,144,131.90
    District: District 4

    Contracts (1) Progress
    # 79873 -- Construction Contract
    Fabrication and Installation of Overhead and Ground Mounted Guide Signs along a Section of Interstate 495. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/05/2009
    Project Initiation Form PIF Entered 05/06/2009
    Project Initiation Form PRC Submitted 05/06/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 06/08/2009
    Project Status Advertised 09/21/2013
    Project Management
    100% Design 100% Package Received 02/12/2013
    25% Design 25% Package Received 11/09/2009
    25% Design 25% Package Comments to DE 01/06/2010
    25% Design 25% Package Approved 01/05/2010
    75% Design 75% Package Received 06/10/2010
    75% Design 75% Package Comments to DE 07/22/2010
    75% Design 75% Plans Approved 07/20/2010
    Final Design PS&E Received 08/28/2013
    Final Design PS&E to FAPRO 09/09/2013
    Consultant Contract Process Scope to DE 05/07/2009
    Consultant Contract Process NTP Issued 06/03/2009
    Consultant Contract Process Workhours Approved 06/02/2009