HARDWICK- RESURFACING & RELATED WORK ON ROUTE 32, FROM 3,000 FT EAST OF ROUTE 32A TO BARRE T.L.
The project consists of coldplaning and resurfacing sections of Route 32 from Upper Church Street northerly to the Barre Town Line for an approximate distance of 6 miles.
Location:
  • Town of Hardwick
  • Resident Engineer: Stefan Toth
    Construction Contract Value: $1,495,805.00
    Construction Bid Price: $1,298,546.80
    Initial Construction Estimate: $1,853,445.50
    District: District 2

    Contracts (1) Progress
    # 62370 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 32 (Lower and Barre Roads). (ARRA Project) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/25/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/20/2009
    Project Initiation Form PIF Entered 06/02/2009
    Project Initiation Form PRC Submitted 07/24/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Status Advertised 01/16/2010
    Project Management
    100% Design 100% Package Received 12/23/2009
    100% Design 100% Package Comments to DE 12/28/2009
    75% Design 75% Package Received 10/26/2009
    75% Design 75% Package Comments to DE 11/20/2009
    Final Design PS&E Received 01/06/2010
    Final Design PS&E to FAPRO 01/11/2010