Project Description:
HAVERHILL- RIVERWALK CONSTRUCTION (BRADFORD SECTION), FROM ROUTE 125 TO COUNTY ROAD
The project is part of the planned 2.5 mile Haverhill Riverwalk. This section is a rail to trail project on property acquired from the Pan Am RR funded by EOTPW. The project begins at the Route 125 bridge over the Merrimack River and ends at the Gonzalian Bridge near the MBTA commuter rail station in Bradford. The section is approximately 3700 feet long. A linear park and interpretive elements are planned as well as several gateway entrances and parking.
Location:
  • City of Haverhill
  • Resident Engineer: Ahmad Rafieizadeh
    Construction Contract Value: $2,464,119.83
    Construction Bid Price: $2,245,493.49
    Initial Construction Estimate: $2,258,000.00
    District: District 4

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 85007 -- Construction Contract
    Riverwalk Construction and Related Work (Including Lighting and Surveillance Fixtures) (Bradford Section) between Route 125 and County Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/27/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/04/2009
    Project Initiation Form PIF Entered 06/05/2009
    Project Initiation Form PRC Submitted 06/30/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 05/20/2010
    Project Status Advertised 09/20/2014
    Project Management
    100% Design 100% Package Received 07/31/2014
    100% Design 100% Package Comments to DE 08/27/2014
    25% Design 25% Package Received 03/15/2013
    25% Design 25% Package Comments to DE 06/25/2013
    25% Design Design Public Hearing 02/12/2014
    75% Design 75% Package Received 04/15/2014
    75% Design 75% Package Comments to DE 06/19/2014
    Final Design PS&E Received 09/15/2014
    Final Design PS&E to FAPRO 09/16/2014