WEYMOUTH- INTERSECTION IMPROVEMENTS @ MIDDLE STREET, LIBBEY INDUSTRIAL PARKWAY AND TARA DRIVE
The project will install traffic signals at the intersection of Middle Street, Libbey Industrial Parkway and Tara Drive. The project will include pavement rehabilitation, lane reconfiguration, sidewalk and wheelchair ramp installation/repair/reconstruction, installation and/or resetting of granite curbing and installation of signs and pavement markings. Since the side streets of this 4-way intersection are off-set, each side street will operate on a separate phase.
Location:
  • Town of Weymouth
  • Construction Begins: Winter 2016/2017
    Resident Engineer: Roderick Connelly III
    Construction Bid Price: $957,729.69
    District: District 6

    Contracts (1) Progress
    # 97588 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) Middle Street at Tara Drive & Libbey Industrial Parkway. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/25/2017
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/04/2009
    Project Initiation Form PIF Entered 07/23/2009
    Project Initiation Form PRC Submitted 07/24/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/03/2009
    Project Status Advertised 08/27/2016
    Project Management
    100% Design 100% Package Received 06/21/2016
    100% Design 100% Package Comments to DE 07/25/2016
    25% Design 25% Package Received 01/13/2010
    25% Design 25% Package Comments to DE 04/12/2013
    25% Design Design Public Hearing 10/24/2012
    75% Design 75% Package Received 09/04/2013
    75% Design 75% Package Received 03/04/2016
    75% Design 75% Package Comments to DE 01/17/2014
    75% Design 75% Package Comments to DE 04/20/2016
    Final Design PS&E Received 08/17/2016
    Final Design PS&E to Peer Reviewer 08/17/2016
    Final Design PS&E to FAPRO 08/22/2016