Project Description:
BOSTON- CAMBRIDGE- NORTH BANK BRIDGE CONSTRUCTION, B-16-302=C-01-028, RIVERWALK OVER MBTA
This project consists of three main components: the North Bank Bridge, the Leonard P. Zakim Bridge Underbridge Plaza (north and south banks) and the North Point Park Expansion. The North Bank Bridge consists of a new bicycle/pedestrian bridge connecting East Cambridge to City Square in Charlestown along the Charles River waterfront. This unique and signature sinusoidal bridge will compliment the adjacent iconic Zakim Bridge and provide a much needed pedestrian connection between the North Point and Paul Revere Parks. The Leonard P. Zakim Bridge Underbridge Plaza is a designed green space utilizing existing granite to create cobble plazas and walkways to feature several art elements along the river’s edge. The North Point Park Expansion will greatly expand the existing North Point Park while providing an area for parking and ease of access for patrons. The upper area of this park will also provide a maintenance facility and an update to existing buildings to enable better management of this increased green space area.
Location:
  • City of Boston
  • City of Cambridge
  • Resident Engineer: Robert O'Neil
    Construction Contract Value: $27,907,990.00
    Construction Bid Price: $25,354,900.00
    Initial Construction Estimate: $30,876,365.65
    District: District 4

    Contracts (1) Progress
    # 60856 -- Construction Contract
    North Bank Bridge Construction (B-16-302=C-01-028) - River Walk over the Millers River and the MBTA Railroad. (ARRA Project) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/30/2009
    Contract Information
    Project Designer: Other
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/12/2009
    Project Initiation Form PIF Entered 06/12/2009
    Project Initiation Form PRC Submitted 06/15/2009
    Project Status Advertised 09/19/2009
    Project Management
    Final Design PS&E Received 06/22/2009
    Final Design PS&E Received 08/24/2009
    Final Design PS&E to FAPRO 08/25/2009