Project Description:
EASTHAMPTON- RAIL-TRAIL & BRIDGE CONSTRUCTION, E-05-028, MANHAN RAIL TRAIL OVER THE MANHAN RIVER
The purpose of this project is to complete the connection of the Manhan Rail Trail between Northampton and Easthampton (see project # 604207). The project will include construction of approximately 900 feet of multi-use path and 160 feet long bridge.
Location:
  • Town of Easthampton
  • Resident Engineer: Joseph Burek
    Construction Contract Value: $755,068.00
    Construction Bid Price: $679,226.00
    Initial Construction Estimate: $883,264.50
    District: District 2

    Contracts (2) Progress
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 67666 -- Construction Contract
    Construction of a Section of the Manhan Rail Trail (Including Bridge (E-05-028) (Steel) over the Manhan River). Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/21/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/29/2009
    Project Initiation Form PIF Entered 06/29/2009
    Project Initiation Form PRC Submitted 06/29/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/10/2009
    Project Status Advertised 09/18/2010
    Project Management
    100% Design 100% Package Received 08/13/2010
    100% Design 100% Package Comments to DE 08/26/2010
    25% Design 25% Package Comments to DE 08/04/2010
    75% Design 75% Package Received 06/23/2010
    75% Design 75% Package Comments to DE 07/06/2010
    Final Design PS&E Received 09/14/2010
    Final Design PS&E to FAPRO 09/14/2010