QUINCY- INTERSECTION & SIGNAL IMPROVEMENTS AT HANCOCK STREET & EAST/WEST SQUANTUM STREETS
The project consists of widening and improvements to the intersection of Hancock Street with East and West Squantum Streets. The project will also include improvements along Hancock Street to the MBTA access drive. The existing mid block pedestrian signal will be upgraded.
Location:
  • City of Quincy
  • Resident Engineer: Ryan Johnson
    Construction Contract Value: $4,469,045.00
    Construction Bid Price: $4,579,475.66
    Initial Construction Estimate: $3,891,350.00
    District: District 6

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 81429 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along Hancock, East and West Squantum Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/18/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    Project Construction Start Date is contingent upon project being scheduled on the STIP.
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/29/2009
    Project Initiation Form PIF Entered 06/29/2009
    Project Initiation Form PRC Submitted 07/01/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/03/2009
    Project Status Advertised 03/15/2014
    Project Management
    100% Design 100% Package Received 01/08/2013
    100% Design 100% Package Comments to DE 05/17/2013
    25% Design 25% Package Received 02/02/2010
    25% Design Design Public Hearing 03/08/2011
    75% Design 75% Package Received 07/15/2011
    Final Design PS&E Received 11/20/2013
    Final Design PS&E to FAPRO 12/18/2013