Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
FREETOWN- INTERSECTION IMPROVEMENTS AT COUNTY ROAD, CHACE ROAD & MASON ROAD
Work on this project includes the installation of a roundabout to channelize traffic and enhance safety at the intersection of County Road, Chace Road and Mason Road.
Location:
  • Town of Freetown
  • Resident Engineer: Alfredo Nunez
    Construction Contract Value: $1,074,479.00
    Construction Bid Price: $875,808.65
    Initial Construction Estimate: $1,004,706.25
    District: District 5

    Contracts (1) Progress
    # 65826 -- Construction Contract
    Intersection Improvements (Roundabout Construction) – County Road at Chace and Mason Roads. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/21/2010
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/29/2009
    Project Initiation Form PIF Entered 06/29/2009
    Project Initiation Form PRC Submitted 06/29/2009
    Project Status Advertised 06/26/2010
    Project Management
    100% Design 100% Package Received 03/04/2010
    100% Design 100% Package Comments to DE 04/21/2010
    25% Design 25% Package Received 03/27/2009
    25% Design 25% Package Comments to DE 06/19/2009
    25% Design Design Public Hearing 08/05/2009
    75% Design 75% Package Received 11/12/2009
    75% Design 75% Package Comments to DE 02/17/2010
    Final Design PS&E Received 05/06/2010
    Final Design PS&E to FAPRO 06/23/2010