Project Description:
WORCESTER- INTERSECTION IMPROVEMENTS AT WINTHROP STREET & PROVIDENCE STREET, VERNON STREET & GRANITE STREET
The project involves reconstruction/resurfacing of .32 miles of Winthrop Street and improvements to the three intersections, including geometric changes, traffic signals, and widening.
Location:
  • City of Worcester
  • Construction Begins: Spring 2019
    Resident Engineer: Michael Chauvin
    Construction Bid Price: $3,025,252.50
    District: District 3

    Contracts (1) Progress
    # 105833 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Winthrop, Vernon, Providence and Adjacent Streets Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/21/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/06/2009
    Project Initiation Form PIF Entered 07/07/2009
    Project Initiation Form PRC Submitted 07/28/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/03/2009
    Project Status Advertised 09/08/2018
    Project Management
    100% Design 100% Package Received 04/02/2018
    100% Design 100% Package Comments to DE 05/04/2018
    25% Design 25% Package Received 08/23/2013
    25% Design 25% Package Comments to DE 08/18/2016
    25% Design Design Public Hearing 08/09/2016
    75% Design 75% Package Received 11/13/2017
    75% Design 75% Package Received 11/23/2017
    75% Design 75% Package Comments to DE 01/25/2018
    Final Design PS&E Received 07/09/2018
    Final Design PS&E to FAPRO 08/27/2018