Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
IPSWICH- RESURFACING & RELATED WORK ON CENTRAL & SOUTH MAIN STREETS
In Ipswich, the project will reconstruct the roadway between Mineral Street and Poplar Street (3200 feet) to improve the roadway surface. Minor geometric improvements at intersection and pedestrian crossings will be included. Sidewalks and wheelchair ramps will be improved in selected areas for ADA compliance. The drainage system is undersized and will be upgraded.
Location:
  • Town of Ipswich
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2027
    Project Manager: David Shedd
    Estimated Total Contract Cost: $10,504,708.88
    Estimated Total Federal Participating Construction Cost: $10,859,905.50
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4
    Current Status: 25% Package Received (as of 03/29/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: IPSWICH
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $5,702,076 (STBG, TAP)
  • Category FA - Trans. Alternative Prgm (TAP)
    Federal Cost: $584,590.40
    State Cost: $146,147.60
    Total Cost: $730,738.00

    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: IPSWICH
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $5,702,076 (STBG, TAP)
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,977,070.40
    State Cost: $994,267.60
    Total Cost: $4,971,338.00

    Planned Federal FY: 2027
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: IPSWICH
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Adj. TFPC: $5,702,076 (STBG, TAP)
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $4,821,297.60
    State Cost: $1,205,324.40
    Total Cost: $6,026,622.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/07/2009
    Project Initiation Form PIF Entered 07/22/2009
    Project Initiation Form PRC Submitted 07/23/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/03/2009
    Project Management
    25% Design 25% Package Received 11/03/2009
    25% Design 25% Package Received 12/09/2010
    25% Design 25% Package Received 04/30/2018
    25% Design 25% Package Received 04/02/2020
    25% Design 25% Package Received 08/19/2020
    25% Design 25% Package Received 03/29/2023