ARLINGTON- RECONSTRUCTION ON FOREST STREET, FROM WINCHESTER T.L. TO SUMMER STREET
The project will reconstruct Forest Street from the Winchester Town Line to Summer Street. The reconstruction of the corridor will include: pavement reconstruction, upgrade of the existing closed drainage system, consistent edge treatments including granite curbing, sidewalk reconstruction, and the provision of accessible curb cuts.
Location:
  • Town of Arlington
  • Resident Engineer: Paul Pascucci
    Construction Contract Value: $1,501,467.00
    Construction Bid Price: $1,334,006.50
    Initial Construction Estimate: $1,455,380.00
    District: District 4

    Contracts (1) Progress
    # 66085 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Forest Street. (ARRA Project) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/30/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/10/2009
    Project Initiation Form PIF Entered 07/10/2009
    Project Initiation Form PRC Submitted 07/14/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/03/2009
    Project Status Advertised 07/24/2010
    Project Management
    100% Design 100% Package Received 02/08/2010
    100% Design 100% Package Comments to DE 03/12/2010
    25% Design 25% Package Received 11/03/2009
    25% Design 25% Package Comments to DE 12/19/2009
    25% Design Design Public Hearing 12/22/2009
    Final Design PS&E Received 07/12/2010
    Final Design PS&E to FAPRO 07/21/2010