Project Description: |
ARLINGTON- RECONSTRUCTION ON FOREST STREET, FROM WINCHESTER T.L. TO SUMMER STREET
The project will reconstruct Forest Street from the Winchester Town Line to Summer Street. The reconstruction of the corridor will include: pavement reconstruction, upgrade of the existing closed drainage system, consistent edge treatments including granite curbing, sidewalk reconstruction, and the provision of accessible curb cuts.
|
Location: |
|
Resident Engineer: | Paul Pascucci |
Construction Contract Value: | $1,501,467.00 |
Construction Bid Price: | $1,334,006.50 |
Initial Construction Estimate: | $1,455,380.00 |
District: | District 4 |
|