Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WORCESTER- BLACKSTONE CANAL DISTRICT STREETSCAPE IMPROVEMENTS
Proposed improvements include resurfacing, widened sidewalks with upgraded materials, installation of street furniture, including benches, bike racks, and waste receptacles, water elements representing the Blackstone Canal, enhanced signage, plantings and street trees, decorative street lighting, and improved pedestrian crossings.
Location:
  • City of Worcester
  • Resident Engineer: Kevin Troy
    Construction Contract Value: $5,961,641.00
    Construction Bid Price: $5,366,588.10
    Initial Construction Estimate: $6,047,990.00
    District: District 3

    Contracts (3) Progress
    # 54138 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57736 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 66679 -- Construction Contract
    Blackstone Canal District Seascape Improvements (ARRA) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/04/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/14/2009
    Project Initiation Form PIF Entered 07/14/2009
    Project Initiation Form PRC Submitted 07/28/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/03/2009
    Project Status Advertised 09/11/2010
    Project Management
    100% Design 100% Package Received 05/20/2010
    100% Design 100% Package Comments to DE 07/23/2010
    25% Design 25% Package Received 01/22/2010
    25% Design 25% Package Comments to DE 02/12/2010
    25% Design Design Public Hearing 12/15/2009
    Final Design PS&E Received 08/23/2010
    Final Design PS&E to FAPRO 09/07/2010