DISTRICT 5- FABRICATION & INSTALLATION OF SIGNS AND SUPPORTS AT VARIOUS LOCATIONS
This contract will provide for the fabrication and installation of overhead and ground mounted guide signs on as needed basis.
Location:
Resident Engineer: Patrick McKenna
Construction Contract Value: $651,415.00
Construction Bid Price: $634,615.00
Initial Construction Estimate: $745,265.00
District: District 5

Contracts (1) Progress
# 64167 -- Construction Contract
Fabrication and Installation of Overhead and Ground-Mounted Signs at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/11/2010
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/03/2009
    Project Initiation Form PIF Entered 08/03/2009
    Project Initiation Form PRC Submitted 08/03/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 08/31/2009
    Project Status Advertised 05/01/2010
    Project Management
    Final Design PS&E Received 09/23/2009
    Final Design PS&E to FAPRO 09/23/2009