HOLDEN- WEST BOYLSTON- FURNISHING & INSTALLATION OF A SAFETY FENCE AND BRIDGE JOINT REPAIRS ON H-18-029=W-17-027, I-190 OVER QUINAPOXET RIVER
The work under this contract consists of furnishing and installing a safety protective fence, replacing the bridge joint seals, replacing bridge joints assemblies, extension of downspouts and cleaning of bridge scuppers, drainage lines and drainage structures. The contractor will also be required to clean and patch the concrete deterioration in the existing bridge parapet.
Location:
  • Town of Holden
  • Town of West Boylston
  • Resident Engineer: Maksim Cruz
    Construction Contract Value: $1,423,805.00
    Construction Bid Price: $1,255,165.00
    Initial Construction Estimate: $853,762.50
    District: District 3

    Contracts (1) Progress
    # 68305 -- Construction Contract
    Bridge Joint Repairs and Related Work (Including Safety Fence) (H-18-029=W-17-027) (Steel) Interstate 190 over the Quinapoxet River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/27/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/03/2009
    Project Initiation Form PIF Entered 08/04/2009
    Project Initiation Form PRC Submitted 08/07/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 08/28/2009
    Project Status Advertised 03/12/2011
    Project Management
    75% Design 75% Package Received 02/23/2011
    Final Design PS&E Received 03/04/2011
    Final Design PS&E to FAPRO 03/04/2011