Project Description:
LEOMINSTER- SUPERSTRUCTURE REPLACEMENT, L-08-028, HAMILTON STREET OVER ROUTE 2
The work for bridge No. L-08-028 (20W) shall consist of removing the existing bridge deck and replacing it with a new HP cement concrete exposed deck complete with new bridge railing and sidewalk. The existing approach roadways to the bridge will be repaved on both sides.
Location:
  • City of Leominster
  • Resident Engineer: Ryan Davison
    Construction Contract Value: $4,350,449.00
    Construction Bid Price: $3,384,982.35
    Initial Construction Estimate: $4,574,570.00
    District: District 3

    Contracts (4) Progress
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64303 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 73149 -- Construction Contract
    Bridge Superstructure Replacement Br. No. L-08-028 (Steel) Hamilton Street over Route 2. Completed
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/14/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/04/2009
    Project Initiation Form PIF Entered 08/04/2009
    Project Initiation Form PRC Submitted 08/10/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/10/2009
    Project Status Advertised 03/24/2012
    Project Management
    100% Design 100% Package Received 01/31/2012
    100% Design 100% Package Comments to DE 02/15/2012
    75% Design 75% Package Received 06/30/2011
    Final Design PS&E Received 03/15/2012
    Final Design PS&E to FAPRO 03/20/2012