Project Description: |
LEOMINSTER- SUPERSTRUCTURE REPLACEMENT, L-08-028, HAMILTON STREET OVER ROUTE 2
The work for bridge No. L-08-028 (20W) shall consist of removing the existing bridge deck and replacing it with a new HP cement concrete exposed deck complete with new bridge railing and sidewalk. The existing approach roadways to the bridge will be repaved on both sides.
|
Location: |
|
Resident Engineer: | Ryan Davison |
Construction Contract Value: | $4,350,449.00 |
Construction Bid Price: | $3,384,982.35 |
Initial Construction Estimate: | $4,574,570.00 |
District: | District 3 |
|
Bridges
|
|
|
|
|