HOPKINTON- DECK REPLACEMENT, H-23-012, I-90 RAMP OVER I-495
The work shall consist of reconstructing the deck and approach wearing surface; upgrading the bridge rail, bridge transition; upgrading the approach guard rail; replacement of deck joints at the abutments and eliminating/replacing joints over the piers. The work will also include repairing concrete deterioration at existing abutment seats; repairing the deterioration at the piers; cleaning and painting of all structural steel.
Location:
  • Town of Hopkinton
  • Resident Engineer: Anthony Tavalone
    Construction Contract Value: $4,179,742.00
    Construction Bid Price: $3,354,457.00
    Initial Construction Estimate: $4,059,143.00
    District: District 3

    Contracts (3) Progress
    # 55035 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 56818 -- Design -- Services
    Work will consist of providing statewide photogrammetric services on an as need, assignment basis over a period of 60 months. Final
    # 76248 -- Construction Contract
    Bridge Deck Replacement (H-23-012) (Steel) - I-90 Ramp Connector over I-495. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/11/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/04/2009
    Project Initiation Form PIF Entered 08/04/2009
    Project Initiation Form PRC Submitted 08/10/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/10/2009
    Project Status Advertised 11/17/2012
    Project Management
    100% Design 100% Package Received 07/11/2012
    100% Design 100% Package Comments to DE 07/19/2012
    75% Design 75% Package Received 03/19/2011
    75% Design 75% Plans Approved 06/15/2011
    75% Design 75% Plans Complete 06/15/2011
    Final Design PS&E Received 11/01/2012
    Final Design PS&E to FAPRO 11/07/2012
    Consultant Contract Process NTP Issued 03/01/2010
    Consultant Contract Process Workhours Approved 02/26/2010