Project Description: |
HOPKINTON- DECK REPLACEMENT, H-23-012, I-90 RAMP OVER I-495
The work shall consist of reconstructing the deck and approach wearing surface; upgrading the bridge rail, bridge transition; upgrading the approach guard rail; replacement of deck joints at the abutments and eliminating/replacing joints over the piers. The work will also include repairing concrete deterioration at existing abutment seats; repairing the deterioration at the piers; cleaning and painting of all structural steel.
|
Location: |
|
Resident Engineer: | Anthony Tavalone |
Construction Contract Value: | $4,179,742.00 |
Construction Bid Price: | $3,354,457.00 |
Initial Construction Estimate: | $4,059,143.00 |
District: | District 3 |
|
Bridges
|
|
|
|
|