Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- RECONSTRUCTION OF MELNEA CASS BOULEVARD
The project calls for the reconstruction of Melnea Cass Boulevard including improved pedestrian and bicycle facilities, traffic signal operation enhancements, landscaping as well ITS measures to create a Complete Streets design.
Location:
  • City of Boston
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Spring 2020
    Project Manager: Gautam Sen
    Estimated Total Contract Cost: $21,763,545.90
    Estimated Total Federal Participating Construction Cost: $24,128,109.80
    District: District 6
    Current Status: This project has been advertised for construction bids. (as of 08/31/2019 )

    Contracts (1) Progress
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/06/2009
    Project Initiation Form PIF Entered 04/12/2011
    Project Initiation Form PRC Submitted 04/12/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 08/31/2019
    Project Management
    100% Design 100% Package Received 03/05/2019
    100% Design 100% Package Comments to DE 04/30/2019
    25% Design 25% Package Received 06/30/2017
    25% Design 25% Package Comments to DE 11/01/2017
    25% Design Design Public Hearing 03/01/2018
    75% Design 75% Package Received 08/07/2018
    75% Design 75% Package Comments to DE 11/16/2018
    Final Design PS&E Received 06/20/2019
    Final Design PS&E to Peer Reviewer 03/19/2019
    Final Design Peer Review Comments to DE 04/03/2019
    Final Design PS&E to FAPRO 08/19/2019