PITTSFIELD- INTERSECTION IMPROVEMENTS & TRAFFIC SIGNAL INSTALLATION AT NORTH STREET @ LOWER WAHCONAH STREET
Proposed project will include new traffic signals, control equipment, associated geometric improvements and pavement markings for stop lines, auxiliary lanes, transitions and crosswalks; and regulatory signage. AAB compliant ramps will be installed at all crossing locations; and a new pedestrian crossing of North Street, south of the intersection, will be created. The relocation and improvement of an existing BRTA bus shelter on the northwest corner of intersection is also being considered as part of the project.
Location:
  • City of Pittsfield
  • Resident Engineer: Thomas Viscuso
    Construction Contract Value: $75,371.00
    Construction Bid Price: $628,342.00
    Initial Construction Estimate: $699,549.20
    District: District 1

    Contracts (2) Progress
    # 64302 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 69633 -- Construction Contract
    PITTSFIELD - Intersection Improvements (Including Traffic Signals) at North and Wahconah Streets Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/14/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/10/2009
    Project Initiation Form PIF Entered 08/10/2009
    Project Initiation Form PRC Submitted 08/10/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Review Committee Letter 09/17/2009
    Project Status Advertised 07/02/2011
    Project Management
    100% Design 100% Package Received 05/02/2011
    100% Design 100% Package Comments to DE 05/27/2011
    25% Design 25% Package Received 05/19/2010
    25% Design 25% Package Received 07/06/2010
    25% Design 25% Package Received 07/26/2010
    25% Design 25% Package Comments to DE 06/25/2010
    25% Design 25% Package Comments to DE 09/15/2010
    25% Design 25% Package Rejected 06/25/2010
    25% Design Design Public Hearing 11/10/2010
    75% Design 75% Package Received 01/07/2011
    75% Design 75% Package Comments to DE 02/04/2011
    Final Design PS&E Received 06/25/2011
    Final Design PS&E to FAPRO 06/28/2011
    Consultant Contract Process Scope to DE 06/01/2009