Project Description:
ARLINGTON- SAFE ROUTES TO SCHOOL (DALLIN SCHOOL)
New concrete sidewalks with granite curbing will be constructed on the west side of George Street and the west side of Renfrew Street in Arlington. New ADA-compliant ramps will be constructed at the intersections of George Street at Florence Avenue and Oakland Avenue, and Renfrew Street at Florence Avenue and Oakland Avenue. A new concrete sidewalk with granite curbing is also proposed on one side of George Street Extension and new ADA-compliant ramps are proposed for the intersection of Rhinecliff Street / Dow Avenue / George Street Extension. New crosswalks and applicable signage are proposed for each intersection.
Location:
  • Town of Arlington
  • Resident Engineer: James Herrick
    Construction Contract Value: $458,057.00
    Construction Bid Price: $389,970.85
    Initial Construction Estimate: $420,314.00
    District: District 4

    Contracts (1) Progress
    # 67527 -- Construction Contract
    Roadway and Sidewalk Construction along Sections of George and Renfrew Streets and Dow and Florence Avenues (Safe Routes to School – Dallin School). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/04/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Safe Routes to Schools
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/10/2009
    Project Initiation Form PIF Entered 08/10/2009
    Project Initiation Form PRC Submitted 08/11/2009
    Project Review Committee PRC Approved 08/13/2009
    Project Status Advertised 09/04/2010
    Project Management
    100% Design 100% Package Received 05/17/2010
    100% Design 100% Package Comments to DE 07/02/2010
    25% Design 25% Package Received 11/13/2009
    25% Design 25% Package Comments to DE 03/26/2010
    25% Design Design Public Hearing 04/08/2010
    75% Design 75% Package Received 11/13/2009
    75% Design 75% Package Comments to DE 03/26/2010
    Final Design PS&E Received 07/22/2010
    Final Design PS&E to FAPRO 09/01/2010