Project Description:
FALL RIVER- SCHEDULED & EMERGENCY DECK & STEEL REPAIRS ON ROUTE 79 VIADUCT & I-195 RAMPS
This project is intended for deck and steel repair maintenance at the Route 79 viaduct & I-195 Ramps.
Location:
  • City of Fall River
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Michael O'Dowd
    Estimated Total Contract Cost: $10,991,705.48
    Estimated Total Federal Participating Construction Cost: $8,000,000.00
    District: District 5
    Current Status: This project has been advertised for construction bids. (as of 03/06/2010 )

    Contracts (2) Progress
    # 55034 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 63320 -- Construction Contract
    Bridge Rehabilitation and Emergency Repairs (F-2-59) (Steel) – Route 79 Viaduct (Western Expressway) and the I-195 Ramps. (ABP)

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/10/2009
    Project Initiation Form PIF Entered 08/10/2009
    Project Initiation Form PRC Submitted 08/10/2009
    Project Initiation Form PRC Submitted 08/10/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Status Advertised 03/06/2010