Project Description:
WALPOLE- BRIDGE REMOVAL, W-03-003, COMMON STREET OVER ABANDONED RAILROAD
Work on this project will consist of removal of an obsolete bridge and filling in the existing railroad bed with a new roadway section with 3:1 side slopes.
Location:
  • Town of Walpole
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Aidee Cira
    Estimated Total Contract Cost: $445,372.06
    Estimated Total Federal Participating Construction Cost: $497,375.50
    District: District 5
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 05/10/2023 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/11/2009
    Project Initiation Form PIF Entered 08/11/2009
    Project Initiation Form PRC Submitted 08/11/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Management
    25% Design 25% Package Received 03/15/2013
    Consultant Contract Process NTP Issued 05/10/2023