Project Description:
MONTEREY- RESURFACING & RELATED WORK ON ROUTE 23, FROM GREAT BARRINGTON T.L. TO OTIS T.L.
The project consists of resurfacing and related work on Route 23 for 7.14 miles from the Great Barrington town line to the Otis town line. The project is anticipated to be advertised as a "book job" with minimal environmental or Right-of-Way impacts. The roadway section through the village center is proposed to be milled before resurfacing to avoid raising the roadway surface in this area.
Location:
  • Town of Monterey
  • Resident Engineer: Thomas Viscuso
    Construction Contract Value: $4,182,910.00
    Construction Bid Price: $3,495,574.00
    Initial Construction Estimate: $3,464,936.25
    District: District 1

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 82413 -- Construction Contract
    Resurfacing and Related Work along Route 23 (Main Road). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/04/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/11/2009
    Project Initiation Form PIF Entered 09/10/2009
    Project Initiation Form PRC Submitted 09/10/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Status Advertised 05/17/2014
    Project Management
    100% Design 100% Package Received 10/21/2013
    25% Design 25% Package Received 03/29/2010
    25% Design 25% Package Rejected 05/03/2010
    25% Design 25% Package Approved 08/03/2011
    25% Design Design Public Hearing 11/29/2011
    75% Design 75% Package Received 10/30/2012
    75% Design 75% Package Comments to DE 09/20/2013
    Final Design PS&E Received 05/08/2014