WILLIAMSTOWN- RECONSTRUCTION & RELATED WORK ON ROUTE 43 (WATER STREET)
The proposed project will reconstruct and widen Water Street from Heating Plant Drive to 800 ft south of Meachum Street (0.43 mi). The current proposal calls for widening the roadway from 27 ft to 31 ft. Also proposed is a parallel parking lane (8 ft) on the west side of the roadway from Heating Plant Drive to Meachum St. The existing deteriorated bituminous concrete sidewalks and curbs will be replaced with 5’ wide cement concrete sidewalks and granite curbing on both sides of the roadway. The existing pavement will be milled and the entire roadway will be overlaid curb to curb. Streetscape elements including new lighting and a bus stop/shelter are also proposed.
Location:
  • Town of Williamstown
  • Construction Begins: Winter 2017/2018
    Resident Engineer: Darin Aitken
    Construction Bid Price: $1,743,356.50
    District: District 1

    Contracts (2) Progress
    # 102062 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Route 43 (Water Street). Completed
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/23/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/11/2009
    Project Initiation Form PIF Entered 08/11/2009
    Project Initiation Form PRC Submitted 08/11/2009
    Project Review Committee PRC Approved 09/09/2009
    Project Review Committee Letter 09/10/2009
    Project Status Advertised 08/26/2017
    Project Management
    100% Design 100% Package Received 11/08/2016
    100% Design 100% Package Comments to DE 12/15/2016
    25% Design 25% Package Received 01/22/2010
    25% Design Design Public Hearing 09/02/2010
    75% Design 75% Package Received 12/08/2014
    75% Design 75% Package Comments to DE 02/25/2015
    Final Design PS&E Received 04/27/2017
    Final Design PS&E to Peer Reviewer 05/01/2017
    Final Design Peer Review Comments to DE 05/08/2017
    Final Design PS&E Received - Resub 1 06/28/2017