DISTRICT 2- HIGHWAY CLEANING ON SECTIONS OF I-91 & I-291 (GREATER SPRINGFIELD AREA)
The work to be done under this contract shall consist of furnishing the labor, materials, equipment and transportation necessary for the removal and satisfactory disposal of all sand from winter snow and ice control operations, leaves, refuse and other debris which has accumulated within the paved median strips of Interstate 91 and 291 in Greater Springfield.
Location:
  • City of Chicopee
  • Town of Longmeadow
  • City of Springfield
  • Town of West Springfield
  • Resident Engineer: Jon Widdison
    Construction Contract Value: $102,863.00
    Construction Bid Price: $77,863.00
    Initial Construction Estimate: $104,687.50
    District: District 2

    Contracts (1) Progress
    # 67422 -- Construction Contract
    Highway Cleaning on Sections of Interstate 91 and 291. (RE-ADVERTISED) 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/04/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/27/2009
    Project Initiation Form PIF Entered 08/27/2009
    Project Initiation Form PRC Submitted 08/27/2009
    Project Status Advertised 06/19/2010
    Project Status Advertised 11/20/2010
    Project Management
    Final Design PS&E Received 09/24/2009