Project Description:
SALISBURY- RAIL-TRAIL CONNECTOR CONSTRUCTION TO THE ROUTE 1 (GILLIS) BRIDGE
The project will create a safe pedestrian and bicycle crossing at the northerly terminus of the Route 1 bridge over the Merrimack River (Gillis Bridge) by constructing a trail adjacent to and under the Gillis Bridge and a sidewalk along Friedenfels Road. The path will connect the Salisbury Rail Trail and the Clipper City Trail in Newburyport.
Location:
  • Town of Salisbury
  • Resident Engineer: Paul Cameron
    Construction Contract Value: $1,122,591.00
    Construction Bid Price: $1,015,547.98
    Initial Construction Estimate: $770,000.00
    District: District 4

    Contracts (2) Progress
    # 43766 -- Design -- Hwy Eng Open End
    Preparation and review of Layout plans and written descriptions on various projects statewide. Final
    # 71087 -- Construction Contract
    Bike Path Construction on Friedenfels Road and along Route 1 (Bridge Road) at the Gillis Bridge. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/30/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2009
    Project Initiation Form PIF Entered 01/15/2010
    Project Initiation Form PRC Submitted 01/19/2010
    Project Review Committee PRC Approved 02/11/2010
    Project Review Committee Letter 02/26/2010
    Project Status Advertised 09/17/2011
    Project Management
    100% Design 100% Package Received 07/18/2011
    100% Design 100% Package Comments to DE 08/24/2011
    25% Design 25% Package Received 03/04/2011
    25% Design 25% Package Comments to DE 04/20/2011
    25% Design Design Public Hearing 04/05/2011
    75% Design 75% Package Received 07/18/2011
    Final Design PS&E Received 08/29/2011
    Final Design PS&E to FAPRO 09/07/2011