SPRINGFIELD- RECONSTRUCTION OF EDWARDS STREET, SPRING STREET & ELLIOT STREET
The roadways and sidewalks in the area of DCAM's proposed data center are in need of repair. Under this project Edwards, Elliot, and Spring Street will be resurfaced, curb will be removed and reset or replaced, sidewalks will be repaired or reconstructed, wheelchair ramps will be reconstructed, new street lighting installed and new pavement markings, including parking spaces, will be applied.
Location:
  • City of Springfield
  • Resident Engineer: Antonio Baltazar
    Construction Contract Value: $1,359,944.00
    Construction Bid Price: $1,431,315.00
    Initial Construction Estimate: $1,555,928.50
    District: District 2

    Contracts (2) Progress
    # 64304 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 74150 -- Construction Contract
    Roadway Reconstruction and Related Work on Sections of Edward, Spring and Elliot Streets Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/02/2012
    Contract Information
    Project Designer: Municipality
    Funding Source: SECTION 125
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/03/2009
    Project Initiation Form PIF Entered 09/21/2009
    Project Initiation Form PRC Submitted 09/21/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Status Advertised 06/30/2012
    Project Management
    100% Design 100% Package Received 04/18/2012
    100% Design 100% Package Comments to DE 06/08/2012
    25% Design 25% Package Received 04/27/2011
    25% Design 25% Package Comments to DE 10/04/2011
    25% Design Design Public Hearing 11/15/2011
    75% Design 75% Package Received 01/11/2012
    75% Design 75% Package Comments to DE 03/29/2012
    Final Design PS&E Received 06/21/2012
    Final Design PS&E to FAPRO 06/26/2012