Project Description:
WORCESTER- BLACKSTONE RIVER BIKEWAY (SEGMENT 7), INCLUDING BRIDGE REHAB, W-44-041, MCGRATH BOULEVARD OVER MADISON STREET
The project extends from Quinsigamond Avenue along Lamartine St., Hermon St., and Francis J. McGrath Blvd. to the intersection of Franklin and Green St. in Worcester, a distance of 0.82 miles. There it connects to an existing paved pathway to Union Station.
Location:
  • City of Worcester
  • Construction Begins: Spring 2019
    Resident Engineer: Anthony Maglione
    Construction Bid Price: $6,181,022.00
    District: District 3

    Contracts (1) Progress
    # 105829 -- Construction Contract
    Construction of the Blackstone River Bikeway (Including Signals and Bridge No. W-44-041) (Segment 7) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/29/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/08/2009
    Project Initiation Form PIF Entered 08/19/2010
    Project Initiation Form PRC Submitted 08/19/2010
    Project Review Committee PRC Approved 08/13/2009
    Project Status Advertised 09/08/2018
    Project Management
    100% Design 100% Package Received 02/05/2018
    100% Design 100% Package Comments to DE 04/03/2018
    25% Design 25% Package Received 01/02/2013
    25% Design 25% Package Comments to DE 02/11/2014
    25% Design 25% Package Comments to DE 07/08/2015
    25% Design Design Public Hearing 06/03/2014
    75% Design 75% Package Received 03/04/2015
    75% Design 75% Package Comments to DE 04/13/2015
    Final Design PS&E Received 08/20/2018
    Final Design PS&E to Peer Reviewer 03/29/2018
    Final Design Peer Review Comments to DE 04/24/2018
    Final Design PS&E to FAPRO 08/27/2018