Project Description: |
NEWTON- SOUND BARRIER INSTALLATION ON I-90 (EB), ADJACENT CURVE & CRESCENT STREETS
The purpose of this project is to furnish and install a wood sound barrier adjacent to Curve and Crescent Streets by the Crescent Street Playground within the MassPike Right-Of-Way.
|
Location: |
|
Resident Engineer: | Carmine LaVita |
Construction Contract Value: | $1,313,180.00 |
Construction Bid Price: | $1,193,800.00 |
Initial Construction Estimate: | $1,556,325.00 |
District: | District 4 |
|
Bridges |
|
|
|
|