| Project Description: |
BOSTON- DISCHARGE DRAIN PIPE REPLACEMENT IN THE I-90/TED WILLIAMS TUNNEL (CRC 3)
The purpose of this project is to replace an existing Ted Williams Tunnel storm water discharge pipe.
|
| Location: |
|
| Construction Begins: | Spring 2010 |
| Resident Engineer: | Pasquale Mele![]() |
| Construction Contract Value: | $641,585.00 |
| Construction Bid Price: | $557,900.00 |
| Initial Construction Estimate: | $560,000.00 |
| District: | District 6 |
|
Bridges
|
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||