Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CHARLEMONT- CULVERT REPLACEMENT, C-05-016 & C-05-017, MOHAWK TRAIL (ROUTE 2) OVER OXBOW BROOK AND WILDER BROOK
Existing culverts will be replaced by CIP rigid frames. One lane of traffic will be maintained. Stage construction will be required. LRFD Code will be used for design.
Location:
  • Town of Charlemont
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: David Shedd
    Estimated Total Contract Cost: $1,776,939.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    No TIP Data Available For This Project