Project Description:
CHARLEMONT- CULVERT REPLACEMENT, C-05-016 & C-05-017, MOHAWK TRAIL (ROUTE 2) OVER OXBOW BROOK AND WILDER BROOK
Existing culverts will be replaced by CIP rigid frames. One lane of traffic will be maintained. Stage construction will be required. LRFD Code will be used for design.
Location:
  • Town of Charlemont
  • Resident Engineer: Timothy Moore
    Construction Contract Value: $1,776,939.00
    Construction Bid Price: $1,541,763.00
    Initial Construction Estimate: $1,993,850.00
    District: District 1

    Contracts (4) Progress
    # 43766 -- Design -- Hwy Eng Open End
    Preparation and review of Layout plans and written descriptions on various projects statewide. Final
    # 44056 -- Design -- Bridge Rehab/Recon/New Const
    Provide design services for the rehabilitation of existing bridges, structural evaluations and emergency design support services. Final
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 71090 -- Construction Contract
    2 Bridge Replacements (C-05-016 & C-05-017) (Concrete Culverts) - Route 2 (Mohawk Trail) over Oxbow and Wilder Brooks. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/09/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/29/2009
    Project Initiation Form PIF Entered 09/29/2009
    Project Initiation Form PRC Submitted 09/29/2009
    Project Review Committee PRC Approved 10/30/2009
    Project Review Committee Letter 10/30/2009
    Project Status Advertised 09/17/2011
    Project Management
    100% Design 100% Package Received 05/10/2011
    100% Design 100% Package Comments to DE 06/30/2011
    25% Design 25% Package Received 11/24/2010
    25% Design 25% Package Comments to DE 11/16/2010
    25% Design 25% Package Comments to DE 11/16/2010
    75% Design 75% Package Received 11/24/2010
    75% Design 75% Package Comments to DE 02/18/2011
    Final Design PS&E Received 08/01/2011