Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DARTMOUTH- IMPROVEMENTS ON GRAND ARMY OF THE REPUBLIC HIGHWAY (U.S. ROUTE 6) AND FAUNCE CORNER ROAD
This project is the first phase of corridor improvements on Route 6 and Faunce Corner Road. Work on this project consists of traffic signal upgrades and geometric improvements at the intersection of Rte 6/Faunce Corner Road/Old Westport Road and Faunce Corner Road with the Mall Drive. Corridor improvements on Faunce Corner Road from the Route 6 intersection to the Mall Drive intersection are included in project. The project will improve safety and operation on the corridor as well as pedestrian and bicycle accommodation. Also included are updated traffic signs, pavement markings and drainage improvements. The next phase will include realigning Tucker Road with Hathaway Road and Route 6 as well as improvements on the Route 6 corridor.
Location:
  • Town of Dartmouth
  • Resident Engineer: Francis Grenon
    Construction Bid Price: $3,747,747.00
    District: District 5

    Contracts (1) Progress
    # 89911 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Faunce Corner Mall Road and Route 6 (Grand Army of the Republic Highway) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/21/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Received 04/03/2009
    Project Need Form PNF Entered 09/30/2009
    Project Need Form PNF Approved 06/04/2009
    Project Initiation Form PIF Entered 08/03/2010
    Project Initiation Form PRC Submitted 08/03/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/23/2010
    Project Status Advertised 08/01/2015
    Project Management
    100% Design 100% Package Received 04/24/2015
    100% Design 100% Package Comments to DE 05/28/2015
    25% Design 25% Package Received 05/18/2012
    25% Design 25% Package Comments to DE 04/12/2013
    25% Design Design Public Hearing 07/17/2014
    75% Design 75% Package Received 11/05/2014
    75% Design 75% Package Comments to DE 03/12/2015
    Final Design PS&E Received 07/02/2015
    Final Design PS&E to FAPRO 07/29/2015