| Project Description: |
ARLINGTON- CONSTRUCTION OF A NEW DISTRICT FOUR ADMINISTRATION BUILDING ON APPLETON STREET
Work on this project includes the renovation of garage space to office space and upgrading the facility to meet ADA/AAB.
|
| Location: |
|
| Construction Begins: | Spring 2025 |
| Resident Engineer: | Michael Pavao![]() |
| Construction Bid Price: | $37,613,024.00 |
| District: | District 4 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
|||||||||||||||||||||||||||||||||||||||||